Proposition MVS would pay for improvements to school facilities
On Tuesday, April 7, Mt. Vernon residents will be asked to approve a tax levy, called Proposition MVS, which will allow the Mt. Vernon R-V School District to finance renovations and additions to its buildings. The tax levy, $0.35 for every $100 of assessed property, would allow the district to borrow $11.5 million for the building improvements.
Scott Cook, superintendent of schools, said that every school building in the district has a need for renovations or additions of some kind. Improvements are as follows:
Mt. Vernon Elementary School
At the elementary school, Cook said, the district would: recover or replace roofs over most every part of campus, rewire the campus to meet code and improve safety and efficiency, ensure the entire building has “fire alarm coverage under a unified system,” reconstruct the entryway “to provide the utmost student safety” and “remove asbestos from areas where it needs to be mitigated.”
Mt. Vernon Intermediate School
At the intermediate school, a new entry system would be installed.
“We would be adding an improved, secure entry system to provide the best scenario for student and staff safety,” Cook said.
Mt. Vernon Middle School
The middle school would likewise receive many of the same renovations, such as roof replacement, rewiring, and asbestos removal. Other renovations would include: an improved secure entry system, improve drainage on the north end of campus to prevent water from settling there, and the installation of a fire alarm system.
“The middle school does not currently have any fire alarm system,” Cook said.
Mt. Vernon High School
The high school building would have its roof replaced.
“We would be replacing the roof over a majority of the campus,” Cook said. “The flat roofed areas are all in dire need of replacement.”
Cook said another addition to the high school would be a new strength and conditioning classroom built on the south end of the building.
“For the past 23 years we have used the mezzanine area in the gym for this classroom,” he said. “The mezzanine was not built to endure the stress of weight equipment and has begun to show a great deal of wear and tear as a result. An engineering firm evaluated the area over the summer of 2019 and recommended we move this classroom away from the mezzanine as they did not believe it would safely hold up if we continued to use it for this purpose. As a result, we have temporarily relocated this classroom to a back hallway on the east side of the gym.”
South Campus (south of middle school)
The South Campus would also receive extensive renovations if the levy passes. Like the elementary and middle school buildings, the South Campus would have its roofs repaired and the campus rewired. A fire alarm system would be installed (like the middle school building, it doesn’t have a fire alarm system), as well as a new secure entry system. Other renovations, Cook said, would include the replacement of “decades-old carpet” in the classrooms, and the sealing of the rooftop HVAC units “to prevent them from leaking into the building.”
District Office
Cook also said the district office would be relocated.
“There would be a very minor renovation to relocate the District Office to a portion of the South Campus not used by students,” he said.
Early Childhood
Beyond renovations, Cook said the district would like to add new buildings to the district to better serve students. If the levy passes, he said, the district will be able to build a new Early Childhood Center for three and four-year-old students.
“We had originally planned to renovate the South Campus for this purpose, but found that it would actually be cheaper to build a new building on the elementary campus than to renovate an existing building,” Cook said.
Cook added that an increase enrollment has made the new building necessary.
“As recently as four years ago, our preschool served around 30 students,” he said. “As of this point in the school year, we are serving nearly 80 students with a waiting list that would take enrollment well over 100.”
Additionally, Cook said this would give the young students a better chance of academic success as they continue through the higher grades.
“Our Board and administration believe this is one of the most important programs we have,” he said. “A program that provides our youngest students with a solid foundation of success that helps them meet expectations throughout their entire school career.”
Ag building
Cook said the levy would also help the district to expand the high school agriculture program by allowing the district to renovate the current Agriculture Center and build an expansion on the west side of the building.
“Around 42-percent of our high school students are involved in the MVHS Agriculture Program,” he said. “Due to space constraints we have had to cap enrollment of certain classes and limit the types of programs students are able to experience in vocational agriculture.”
Category:
Lawrence County Record
312 S. Hickory St.
Mt. Vernon, MO, 65712
www.lawrencecountyrecord.com